Full package of design drawings and build specification provided and submitted on behalf of the client for full planning.
Pre-demolition works completed without disruption to ongoing site operations.
Excavation for new foundation base, retaining wall and making good completed without disruption to site operations.
MAP gas Service Bridge installed on Saturday afternoon to keep site disruption to an absolute minimum.
All three tanks delivered and installed by Air Products within a designated 3-hour time window.
Pipework and dedicated service drops to 6 production lines. All installed over 3 weekends and fully commissioned.